Battery update: June 2024
On the 30th of May, we marked a major construction milestone – the energisation of the project’s 275kV substation ! This was achieved ahead of schedule thanks to great commitment and collaboration from the teams at UGL, Powerlink Queensland, Tesla and Neoen Australia.
For the next months, the on-site construction crew will continue the cabling, testing and commissioning of the battery, on track for operations in Q4 2024. You can consult our LinkedIn post on that link.