Neoen acknowledges the Barunggam people, Traditional Owners of the land on which Western Downs Green Power Hub will harvest and store the energy of the sun. We pay our respects to their Elders past and present.

Construction Update: August 2022

Construction continues on site, multiple work fronts are complete while some are progressing well and nearing completion:

  • 100% of underground cable across site is installed;
  • 100% of piles have been installed and the PV tracking structure installation continues, at around 80% complete currently;
  • 100% of inverter stations have been installed;
  • 100% of PV modules have arrived either at port in Brisbane or on site, more than 60% have been installed;
  • Commissioning of the plant is well underway and the plant recently generated in excess of 100 MW.

Should you have any queries or concerns in relation to the works, please don’t hesitate to contact us on 1800 966 133 or email us through the contact page.