Neoen acknowledges the Barunggam people, Traditional Owners of the land on which Western Downs Green Power Hub will harvest and store the energy of the sun. We pay our respects to their Elders past and present.

Construction Update: April, May, June

Construction continues to ramp up on site on multiple work fronts.

  • Underground cable installation across site is ongoing with over 90km of medium voltage (33kV) AC trenches laid with cable across the site;
  • Over 40% of piles have been installed and the PV tracking structure installation is underway, the workforce will ramp up considerably for this activity over the next few weeks
  • The critical substation component is on schedule and the two 300MVA high voltage transformers, 2x main switchrooms and control room were all delivered and installed at site in May.

Should you have any queries or concerns in relation to the works, please don’t hesitate to contact us on 1800 966 133 or email us through the contact page.