Construction Update: April, May, June
Construction continues to ramp up on site on multiple work fronts.
- Underground cable installation across site is ongoing with over 90km of medium voltage (33kV) AC trenches laid with cable across the site;
- Over 40% of piles have been installed and the PV tracking structure installation is underway, the workforce will ramp up considerably for this activity over the next few weeks
- The critical substation component is on schedule and the two 300MVA high voltage transformers, 2x main switchrooms and control room were all delivered and installed at site in May.